At the beginning of a migration project, the team is examining existing workloads and organizational readiness.
Map the activity to the appropriate AWS migration phase.
Which activity belongs in the Assess phase?
The Assess phase evaluates the current environment, dependencies, readiness, business value, and migration priorities before execution.
Detailed explanation
A simultaneous cutover is an execution decision, not an Assess activity, and increases migration risk.
A simultaneous cutover is an execution decision, not an Assess activity, and increases migration risk.
Post-migration cleanup is an operational decision and is not the purpose of the Assess phase.
Post-migration cleanup is an operational decision and is not the purpose of the Assess phase.
Certification scheduling is unrelated to the migration phases.
Certification scheduling is unrelated to the migration phases.
Assess collects current-state, readiness, risk, cost, and business information that informs migration priorities and the plan.
Assess collects current-state, readiness, risk, cost, and business information that informs migration priorities and the plan.
Check official documentation
Compare the following points with the official documentation.
AWS Prescriptive GuidanceのMigration StrategyでAssessフェーズを確認する。
What to confirm
Assessを現状評価と移行計画の入力を集めるフェーズとして説明できる。
Key points
- Assess phase
- Current-state assessment
- Migration priority
Notes
- Environment: AWS公式Prescriptive Guidanceの確認
- Confirm current AWS migration guidance and service conditions in the official documentation.
Foundation review
Assess output
The assessment supplies scope, risks, priorities, and cost information for the migration plan.
Execution boundary
Cutover and cleanup decisions follow assessment rather than defining it.